During phase 1 of Rivian PDC at Waalwijk, DRDS was responsible for the complete refurbishment of the offices and minor adjustments in the warehouse so that Rivian can already be operational and supply its first cars & buses in Europe with parts.
In phase 2, DRDS will build a battery storage facility in the existing warehouse with all associated requirements and further optimise the offices for use.
1
Projectmanagers
16
Weeks
Phase 1: Start March 2022 - completed June 2022.
Following project